Project Number:  1381   ( 1 Award )
Theme:  Transportation: Road
Current Milestone:  Project Close-out Complete
Contact(s):  Alexa Greene (Department of Transportation)
Betty Sorensen (Denali Commission)
Donna Adams (Department of Transportation)
Geri Henricksen (Department of Transportation)
Monica Armstrong (Denali Commission)
Nicole Woicikowfski (Denali Commission)
Peter D. Christensen (Department of Transportation)
Shelley Dykema (Department of Transportation)
Tessa Axelson (Denali Commission)
Reporting: 
Description:  This project will construct Phase II of the 2.5-mile Gambell Evacuation Road and a 6- mile extension of that road, the key subsistence use areas at Akeftapak Bay and Teveghak Bay. A third branch of the project will access the local cemetery. The road will be built to AASHTO standards with an 18-22-foot width and a 25 mph speed design. A crushed gravel surface will be installed. This combination of road segments will significantly improve travel between the community and these three destinations, improving safety and traveler comfort, reducing wear and tear on vehicles and reducing fuel consumption to destinations currently over unimproved tundra.
Progress Report Expenditures
  Funding Expenditures*   %
Denali Commission: $470,869.26 $470,869.26    100%
Other Funding: $8,000,000.00 $8,191,361.48    102%
Communities: 
Name Distressed/
Non-Distressed
Borough ANCSA Region House
District
Senate
District
DCED Profile
Gambell Distressed Unorganized Bering Straits Native Corp. 39 T Gambell

Community Database Online
Additional community information from the State of Alaska, Department of Community and Economic Development
Attachments: 
  Title Date Attachment Type Source
Headquarters - Financial Report - Gambell 01/06/2015 Other Report 
AKSAS Screen Print - Gambell 01/06/2015 Other Report 
Healy - Project Information Sheet 01/06/2015 Other Report 
Headquarters - Financial Report - Gambell 07/15/2014 Other Report 
Headquarters Financial Report - Gambell 05/19/2014 Other Report 
Headquarters Financial Report - Gambell 01/30/2014 Other Report 
Headquarters Financial Report - Gambell 11/04/2013 Other Report 
Gambell - After Photo - 1 11/04/2013 Photo (After Project) Report 
Gambell - After Photo - 2 11/04/2013 Photo (After Project) Report 
Gambell - After Photo - 3 11/04/2013 Photo (After Project) Report 
Gambell - After Photo - 4 11/04/2013 Photo (After Project) Report 
Gambell - After Photo - 5 11/04/2013 Photo (After Project) Report 
Gambell - After Photo - 6 11/04/2013 Photo (After Project) Report 
Gambell - After Photo - 7 11/04/2013 Photo (After Project) Report 
Gambell - After Photo - 8 11/04/2013 Photo (After Project) Report 
Headquarters Financial Report - Gambell 08/01/2013 Other Report 
During Construction_Gambell_6578 08/01/2013 Photo (During Project) Report 
During Construction_Gambell_590 08/01/2013 Photo (During Project) Report 
Headquarters Financial Report - Gambell Evacuation Rd 04/22/2013 Other Report 
Headquarters Financial Report - Gambell 01/31/2013 Other Report 
Email from Donna Adams to Alexa Greene_Informing that HQ is billing FHWA first_0 01/31/2013 Other Report 
Compilation of Bids_Gambell Evac Road 12/31/2012 Other Report 
Construction Plan Set_Gambell 12/31/2012 Other Report 
Headquarters Financial Report - Gambell 12/31/2012 Other Report 
Constuction - BEFORE Photo 12/31/2012 Photo (Before Project) Report 
Constuction - During Photo - 08_22_2012 - #1 12/31/2012 Photo (During Project) Report 
Constuction - During Photo - 08_22_2012 - #2 12/31/2012 Photo (During Project) Report 
Constuction - During Photo - 08_22_2012 - #3 12/31/2012 Photo (During Project) Report 
Constuction - During Photo - 08_22_2012 - #4 12/31/2012 Photo (During Project) Report 
Constuction - During Photo - 08_22_2012 - #5 12/31/2012 Photo (During Project) Report 
Headquarters Financial Report - Gambell 07/24/2012 Other Report 
Monthly Progress Reports for DC - Gambell 07/24/2012 Progress Report Report 
Headquarters Financial Report 05/01/2012 Other Report 
Monthly Progress Report for DC_Gambell 05/01/2012 Progress Report Report 