At-a-Glance for Alaska Energy Authority Project #01152 407063
Iliamna,Newhalen,Nondalton: Tazimina Hydroelectric Upgrade/Repair
Printer-Friendly VersionPrinter-Friendly Version
Project Number:  01152 407063   ( 1 Award )
Theme:  Energy: Other Energy
Current Milestone:  Project Close-out Complete
Contact(s):  AEA Finance (Amy Adler) (Alaska Energy Authority)
Betty Sorensen (Denali Commission)
Chris Mello (Alaska Energy Authority)
David Lockard (Alaska Energy Authority)
Denali Daniels (Denali Commission)
Jodi Fondy (Denali Commission)
Monica Armstrong (Denali Commission)
Rebecca Garrett (Alaska Energy Authority)
Sandra Moller (Alaska Energy Authority)
Reporting: 
Description:  This award of $1,273,543 will provide for repairs and upgrades to the existing Tazimina Hydroelectric Facility which supplies year-round power to Iliamna, Newhalen, and Nondalton, Alaska. (Alaska Energy Authority project number 407063) See award for more scope information.
Progress Report Expenditures
  Funding Expenditures*   %
Denali Commission: $1,270,017.97 $1,270,017.97    100%
Other Funding: $0.00 $0.00    0%
Communities: 
Name Distressed/
Non-Distressed
Borough ANCSA Region House
District
Senate
District
DCED Profile
Iliamna Non-Distressed Lake & Peninsula Borough Bristol Bay Native Corporation 37 S Iliamna
Newhalen Non-Distressed Lake & Peninsula Borough Bristol Bay Native Corporation 37 S Newhalen
Nondalton Distressed Lake & Peninsula Borough Bristol Bay Native Corporation 37 S Nondalton

Community Database Online
Additional community information from the State of Alaska, Department of Community and Economic Development
Attachments: 
  Title Date Attachment Type Source
Close out report 09/30/2014 Project Close-Out Report Report 
Project Expenditure Summary 03/09/2014 Project Close-Out Report Report 
Tazimina Hydro Heated Intake Rack Boiler 10/20/2011 Photo (After Project) Report 
Intake trash rack 09/14/2011 Photo (During Project) Report 
Tazimina Case Study 08/29/2011 Project Narrative Report Report 
Tazimina Hydro Generator Room 08/26/2011 Photo (During Project) Report 
Lake and Pen School Fuel Savings Calculations 06/27/2011 Other Report 
installation of heated trash rack 10/15/2010 Photo (During Project) Report 
Tazimina hydro controls installation #2 09/02/2010 Photo (During Project) Report 
Tazimina hydro controls installation #1 07/02/2010 Photo (During Project) Report 
Tazimina Progress Report 6-10 06/15/2010 Progress Report Report 
Tazimina Hydro Progress Report 4-21-10 04/21/2010 Progress Report Report 
Tazimina progress report 09/29/2009 Progress Report Report 
Tazimina hydro- working at the tailrace 09/29/2009 Photo (During Project) Report 
Tazimina walking mini-hoe down the hill 09/13/2009 Photo (During Project) Report 
Tazimina installing stoplogs 09/13/2009 Photo (During Project) Report 