Alaska Village Electric Cooperative: Brevig Mission Bulk Fuel Upgrades
Award Number:  01055 (1 Project)
Theme:  Energy
Award Performance Period:  05/01/2008 to 09/30/2010
Award Status:  Award Closed Out
Contact(s):  Betty Sorensen (Denali Commission)
Denali Daniels (Denali Commission)
Jodi Fondy (Denali Commission)
Meegan Welch (Alaska Village Electric Cooperative)
Meera Kohler (Alaska Village Electric Cooperative)
Monica Armstrong (Denali Commission)
Scope of Work:  This award provides construction funding in the amount of $2,025,000 to install 243,000 gallons of code-compliant bulk diesel fuel storage for use by the electric power plant that serves the entire village of Brevig Mission. In the future, it is planned that the power plant will also serve the nearby village of Teller, by means of an intertie between Brevig Mission and Teller.
Authorizing Document(s): 08TAP
 
Award Level Funding
Current Amount %
Obligation $2,025,000.00  
Drawdowns $2,025,000.00 100%