Printed: 04/24/2019 02:04 Denali Commission
Project Database System
 
At-a-Glance for Award #1550
Alaska Energy Authority: Remote Power System Upgrade - Akhiok, Alaska
Award Number:  1550 (1 Project)
Theme:  Energy
Award Performance Period:  05/01/2018 to 12/31/2020
Award Status:  Active
Contact(s):  AEA Finance (Amy Adler) (Alaska Energy Authority)
Janet Davis (Denali Commission)
Owen Berklund (Alaska Energy Authority)
Rebecca Garrett (Alaska Energy Authority)
Tim Sandstrom (Alaska Energy Authority)
Tom Wolf (Denali Commission)
Scope of Work:  Design and construction of community power plant in Akhiok, Alaska
Authorizing Document(s):
 
Award Level Funding
Current Amount %
Obligation $1,500,000.00  
Drawdowns $1,383.52 0%