Alaska Village Electric Cooperative: Remote Power System Maintenance and Improvement - Statewide
Award Number:  1545 (1 Project)
Theme:  Energy
Award Performance Period:  05/01/2018 to 09/30/2020
Award Status:  Active
Contact(s):  Alden Worachek (Alaska Village Electric Cooperative)
Forest Button (Alaska Village Electric Cooperative)
Janet Davis (Denali Commission)
Meera Kohler (Alaska Village Electric Cooperative)
Onya Stein (Alaska Village Electric Cooperative)
Tom Wolf (Denali Commission)
Scope of Work:  Perform small maintenance and improvement (M&I) projects at up to 21 gen-set overhauls or replacements at 15 remote power plants. Projects may include gen set replacement, engineer repowers, and facility structural/architectural improvements.
Authorizing Document(s):
 
Award Level Funding
Current Amount %
Obligation $1,950,000.00  
Drawdowns $1,057,769.00 54%